water recycling systems, closed loop recycling, oil water separator, waste water treatment system, industrial water recycling system, ph control system, electrical control panel, oil skimmer, spot free car wash system, industrial pressure washers, clear water system, waste water design, rgf system, jdi inc, washbay solutions, washbay, waste water management, car wash water recycling systems, industrial filtration systems, rgf filters, oil and water separator, industrial water recycling systems, mining equipment wash, theia air, theia water, groundwater remediation, environmental compliance, wash down system, hydroquip, ozonation system, oil sludge treatment, flocculation water treatment, car wash reclaim, wash water recycling, environmental remediation, ch2, waste2water, cleanproducts, carolinachemequip, hydrochemsystem, washbay recycle, rncraftinc, oil absorbant filters, bus wash systems, truck wash system, mining equipment wash, bus closed loop recycling, car wash closed loop recycling, ozone generator, heavy duty equipment wash system, oil water separators in florida, environmental compliance for wastewater, environmental compliance engineer, reverse osmosis, turn key wash system, wash system in container, portable wash systems, portable recycling system, closed loop car wash, industrial truck wash, solids filtration system, train wash system, aircraft wash system, car wash water reuse, palm beach county, jupiter florida, reverse osmosis, school bus wash manufacturer, truck wash manufacturer, control panel manufacturer, pump station control panel system, esd waste2water, waste2water biological treatment systems, rgf washmaster system, wastewater solutions, wash water recycle systems, water recycling environmental centers, high volume washing stations, high pressure demucking station, wash pad hose reels, containerized system, u-shed, high volume car wash recycle system, cw-mod, wm-hvtwas, high volume truck wash recycle system

An Efficient Recycling System for a Marina

Bluepoints Marina

A large marina located in sub-tropical climate conditions needed to be able to provide a

large volume of clean recycled water for boat cleaning under strict environmental conditions.

As the developers of the Bluepoints Marina project in Port Canaveral, Florida, were designing their new facility across the waters from the rocket launch pads of Cape Kennedy, they realized that they would have to bring some expertise on board to solve their boat washdown problems.  Their plans called for 18 individual wash stations capable of operating simultaneously throughout the day, but they had several obstacles to overcome: 

After searching for qualified technical support, the developers selected Waste Water Management, Inc. (WWMI) of Jupiter, Florida, to join their team. WWMI had designed and built similar systems, and was knowledgeable of the environmental and regulatory conditions that would impact the design. 

The system designed by WWMI’s engineers incorporated multiple technologies to accomplish the collection, storage, treatment, disinfection, and redelivery of the wash water.  One of the goals of the Bluepoints Marina’s developers was to design their facility for minimal environmental impact and maximum protection of the surrounding area.  By utilizing a combination of complementary technologies, WWMI was able to meet those goals with fully automated equipment requiring very little oversight while providing reliable service.  “Our task was to bring our expertise to the facility’s design team so that our component of their project met all of their objectives while remaining cost-effective and reliable”, said Steve Prior, President of Waste Water Management.  

Since the equipment and all of the boat washing was located outdoors, both the high heat and frequent heavy rainfalls needed to be taken into account.  A rainwater detection system was incorporated into the equipment design to enable the system to identify and capture the initial rainfall, and then to divert the remainder of the rain water to the storm drain system.  This met the regulatory requirements for initial capture without co-mingling the diverted water with wash water.  

The hot summer days created a number of other design issues.  Equipment and storage tanks needed to be durable enough to withstand the constant sun exposure, the evaporation rate required an automated make-up system and water quality monitoring for increased water salinity, the potential for rapid bacteria growth in the storage tanks resulting in septic water conditions, and the potential for hurricane-level weather conditions were all driving factors in the system design. The equipment and all storage and treatment tanks were painted or coated with UV-inhibited paint, which has successfully withstood all weather conditions for over 4 years.  An integrated pH Control and ORP system manages and controls the large Ozone generator in the system to prevent the water from developing any odors and assisting in the separation of some of the free and dissolved oils in the wash water.  By utilizing a large corona-discharge ozone generator, the water remains disinfected without the need for any added chemical usage that could affect the water quality in the closed-loop system design. Water salinity is monitored visually, although the TDS levels have not proven to be an issue since the system was installed in early 2009.

The wash water collected in the pit system is stored and ozonated, then filtered prior to reuse through deep-bed media filters.  The system was designed as three separate modules, each supplying six wash stations but capable of expansion to additional stations if needed.  Each module contains large automated multi-media filters and carbon filters to polish the water prior to reuse.  These filters, and the entire system, are controlled by an onboard PLC that manages the automatic filter backwashing and delivery pump control.

In order to withstand the constant salt water and highly corrosive ambient conditions, the entire system was manufactured from marine-grade aluminum, stainless steel, and non-ferrous materials.  This has prevented the system from having any deterioration issues to date, despite several intense storms and constant exposure to the salt air.

The performance of the system had far exceeded the expectations of the initial designers.  The water quality has been consistently excellent with no reported odors or adverse quality issues.  The carbon media, which had been projected to require rebedding after 12-18 months, has yet to be changed since the water quality has remained superior. WWMI has maintained a quarterly maintenance contract on the system since the installation, and total costs for all maintenance have been approximately $1000 per year.  The system collects and recycles 100% of all the wash water.  

“This system has been almost trouble-free since the installation, and has saved us thousands of dollars in water bills from the city.  We are extremely happy with the design and operation of the system, and have enjoyed our relationship with WWMI’s highly professional and experienced staff” says Keith Smith, the Marina Manager.  “Other than some minor maintenance issues, we’ve had excellent results with this system and have been able to offer our boat owners reliable washing capability.  The quality of the recycled water has also remained excellent since the system was started up”, added Chip Gaines, the Operations Manager for the Marina.  In fact, Keith recently decided to add some additional wash stations to the system, and hired WWMI to incorporate them into the system. 

Bluepoints Marina has experienced continued growth since it opened, despite local competition and a challenging economy.  As one of the most environmentally friendly marinas in the area, Bluepoints can point to their boat washing operation as one of the many benefits they can offer to the community.  Environmental proactivity, cost-effective water recycling and a customer-oriented focus have helped Bluepoints Marina become a success story.

  • The local municipality could not cost effectively supply the desired 200-gpm flow.

  • The water treatment and storage equipment would be located outdoors in direct sunlight exposed to the sun, humidity, and salt air environment.

  • There were stringent regulatory requirements for the wash water storage and disposal.

  • The developer’s plans included the possibility of a future expansion with additional wash stations.

We are extremely happy with the design and operation of the system, and have enjoyed our relationship with WWMI’s highly professional and experienced staff.

Keith Smith

Port Canaveral, Florida